10:48 AM Training #910: Project Training - IOS Flavoring for multiple company manage
#Check previous task and assign new next updated task. Mohit khandelwal
10:43 AM Bug #911: System software issue- Reinstalled all tools and Android Setup
Software issue, Reinstalled all tools and Android Setup. Mohit khandelwal
07:56 AM Bug #911 (Closed): System software issue- Reinstalled all tools and Android Setup
Karishma Tak

12/03/2021

08:16 AM Feature #884: Behold Code Running & Testing IOS side
#Testing IOS build & share with Jon with new updates.
(with Vandana all case same as android)
Mohit khandelwal

12/02/2021

09:01 AM Training #910: Project Training - IOS Flavoring for multiple company manage
#Give some understanding for flavor management IOS side.
#Test flavors apps
Mohit khandelwal
08:58 AM Feature #884: Behold Code Running & Testing IOS side
Testing IOS build with different Scenario's.
(Vandana's system)
Mohit khandelwal

12/01/2021

08:37 AM Feature #884: Behold Code Running & Testing IOS side

#Testing complete build & finding issue.
#issue Assigning to vandana.
#Assing flavor task IOS side to bhavy's
Mohit khandelwal
07:53 AM Training #910 (Closed): Project Training - IOS Flavoring for multiple company manage
Karishma Tak

11/30/2021

08:35 AM Feature #884: Behold Code Running & Testing IOS side
#Testing IOS side all fixes in Behold app & working functionality Mohit khandelwal

11/29/2021

08:49 AM Feature #884: Behold Code Running & Testing IOS side
#Checks IOS side Behold app working functionality. Mohit khandelwal

11/26/2021

08:39 AM Feature #884: Behold Code Running & Testing IOS side
#Check some points IOS side & Behold app working functionality
(Vandana & Bhavy's system)
Mohit khandelwal

11/25/2021

08:23 AM Feature #899: Firebase notification Sample Test update
#Check some points IOS side given by JON,
#Behold app working functionality.
Mohit khandelwal

11/24/2021

08:55 AM Feature #884: Behold Code Running & Testing IOS side
# Behold app test with android working functionality. Mohit khandelwal

11/23/2021

08:45 AM Feature #899: Firebase notification Sample Test update
#Testing IOS side Behold app working functionality. Mohit khandelwal

11/22/2021

08:09 AM Feature #899: Firebase notification Sample Test update
#Check IOS side Behold app design & functionality. Mohit khandelwal

11/18/2021

01:09 PM Feature #899: Firebase notification Sample Test update
#Bhavy's task page design & IOS side implement after Testing. Mohit khandelwal

11/17/2021

08:01 AM Feature #899: Firebase notification Sample Test update

#Test notification code Generate or Update status Android side.
#Null safety code marge latest dependencies.
Mohit khandelwal

11/16/2021

08:42 AM Feature #884: Behold Code Running & Testing IOS side
#Check Behold Code issues & test calling IOS side/Android side.
(Bhavy's system & vandana system)
Mohit khandelwal
08:05 AM Training #909 (Closed): Angular with Angular Materials
*the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angular m... Karishma Tak
08:05 AM Training #908 (Closed): Angular with Angular Materials
*the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angular m... Karishma Tak
08:03 AM Training #907 (Closed): Angular with Angular Materials
*the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angular m... Karishma Tak
07:57 AM Training #905 (Closed): Angular with Angular Materials
*the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angular m... Karishma Tak
07:43 AM Training #904 (Closed): Angular Materials

https://www.udemy.com/course/angular-material-course/learn/lecture/9614576?start=15#overview
Karishma Tak
03:47 AM Feature #903 (Closed): Disco Training
Karishma Tak
12:23 AM Training #902 (Closed): Angular with Angular Materials
*
the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angular...
Karishma Tak

11/15/2021

11:55 PM Training #901 (Closed): Angular with Angular Materials

*
the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + angul...
Karishma Tak
11:49 PM Training #900 (Closed): Angular with Angular Materials
*
the course has to be completed with angular training , approximate estimated time is 150 hours ( angular + ...
Karishma Tak
08:48 AM Feature #899: Firebase notification Sample Test update

#Check Behold Code issues & test calling.
#some understanding notification code.(Bhavy side)
Mohit khandelwal

11/12/2021

08:33 AM Feature #885: Teamlink Flutter Migration App Code".
#Check Teamlink app testing weekly works Mohit khandelwal
08:32 AM Feature #884: Behold Code Running & Testing IOS side
#Check bhavy side Behold Code implementation notification code Mohit khandelwal

11/10/2021

08:33 AM Feature #899: Firebase notification Sample Test update
Check bhavy side notification code behold project Mohit khandelwal
 